The short answer
In NSW, building work takes one of three routes. Exempt development is minor work that doesn’t need approval if it meets the standards. A complying development certificate (CDC) is a combined planning and construction approval for straightforward work, from your council or a registered certifier, which NSW Planning says can be issued in as little as 20 days. A development application (DA) goes to the consent authority, usually your council, which NSW Planning says takes 70 days on average, and you then need a construction certificate before building starts. For the loan, lenders generally want approved plans, a fixed-price building contract and the builder’s insurance before the first progress payment, so your approval route sets when your loan can start paying your builder. This is general information, not advice.
Waiting on a CDC or a DA?
We can line up your construction loan with your approval, so the plans, contract and insurance are ready when your lender needs them.
Start OnlineFor home loans, you don’t pay us a fee. Lenders pay us a commission if you go ahead with a loan. Lender fees may apply.
These are NSW rules. Your council or a certifier can tell you which route fits your lot and your plans.
The three approval routes in NSW
- Exempt development. NSW Planning says minor, low-impact work may not need planning approval if it meets the exempt development standards in the state policy and complies with the National Construction Code. Its examples include a deck, a garden shed, a carport and a fence. If your project doesn’t meet those standards, you need a CDC or a DA.
- Complying development (a CDC). A fast-track route for straightforward work that meets every relevant standard.
- A development application (DA). The council’s full assessment, for work that needs consent from the council.
What a CDC is
NSW Planning describes complying development as a combined planning and construction approval for straightforward development. Your local council or a registered certifier can issue the complying development certificate, and applications are lodged through the NSW Planning Portal.
- The rules it follows. The standards sit in the State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, often called the Codes SEPP. It includes codes such as the Housing Code for one and two storey homes, the Low Rise Housing Diversity Code and the Pattern Book Development Code 2025. NSW Planning says the Low Rise Housing Diversity Code lets dual occupancies, manor houses and terraces be complying development where they’re permitted with consent. Granny flats have their own standards (see our granny flats guide).
- Every standard, or no CDC. The certifier can only approve it as complying development if the proposal meets all the relevant standards. If it doesn’t, it can’t be approved as complying development.
- Time. NSW Planning says complying development approvals can be issued in as little as 20 days, or 10 days for NSW Housing Pattern Book development.
- Neighbours. The Planning Portal says there are two notifications: one before approval and one before construction.
- No construction certificate needed. NSW Government says you don’t need one if you have a CDC.
- How long it lasts. Campbelltown City Council, for example, says a CDC is valid for 5 years from the date endorsed on it.
Changes are on the way: the Planning Portal says the NSW Government exhibited proposed changes to complying development from 14 May to 24 June 2026, including a pathway for minor variations, and is reviewing feedback.
What a DA is
NSW Planning says local development, the most common type in NSW, runs from home extensions to medium-sized commercial projects, and the consent authority is usually your local council.
- Lodge it. DAs are lodged online through the NSW Planning Portal. NSW Planning says a complete application generally includes a description of the development, estimated costs, any specialist reports, the council’s form and checklist, and the fee.
- Assessment. Advertised development is notified for 14 days. NSW Planning says most councils determine straightforward and complete applications in 40 days or less, and the clock pauses if the council asks for more information. Its complying development page gives 70 days as the average for a DA.
- Determination. The outcome is consent with conditions, a refusal with reasons, or, less commonly, a deferred commencement. Conditions can change your plans, so read them with your certifier and builder. If you’re refused, or a condition is unacceptable, you have 6 months to ask the council for a review or to appeal to the Land and Environment Court.
- Construction certificate. Consent doesn’t mean you can start building. You need a construction certificate from the council or a certifier: detailed building plans, engineering details and specifications that must match the consent. NSW Planning says some conditions must be met first, such as bonds or development contributions.
NSW Planning says a consent lasts 5 years unless the council sets another period.
Before building starts, either way
- A principal certifier. You appoint one before work starts. The certifier inspects the work as it goes.
- Two days’ notice. The council must be told at least two days before work begins.
- An occupation certificate at the end. Your certifier decides whether one can be issued when the work is finished.
| CDC | DA | |
|---|---|---|
| Who approves | Council or a registered certifier | The consent authority, usually your council |
| What it needs | Every relevant Codes SEPP standard met | A full assessment against the council’s plan |
| Time, as NSW Planning states it | As little as 20 days | 70 days on average |
| Before building | No construction certificate needed | Construction certificate needed |
From NSW Planning and NSW Government pages, read 27 November 2026. Your timing depends on your lot, your plans and your council.
Got your approval route sorted, or waiting on it? Let’s line up your construction loan so it’s ready when your builder is.
Book My Home Buying ChatWhat your lender needs before the first progress payment
A construction loan pays your builder in stages, called progress payments, as each part of the job is finished. Each lender sets its own list, but before the first payment, lenders often ask for:
- Approved plans. The CDC and its plans, or the DA consent plus the construction certificate.
- A signed fixed-price building contract. NSW Government says a contract for residential work over $20,000 must include a progress payment schedule and a home building compensation insurance certificate, and that progress payments should reflect work actually done.
- The builder’s licence.
- The builder’s insurance. Where home building compensation cover is required, the builder must give you the certificate ahead of starting work or taking any money from you. The cover protects you if the builder can’t finish the work or fix defects because of insolvency, licence suspension, death or disappearance. A lender may also ask for the builder’s all risk and public liability cover.
- An “as if complete” valuation. The valuer estimates what the finished home will be worth, from the plans and contract. A lender may use the lower of the valuer’s figure for the work and the contract price.
- Your own money first. Some lenders want your own contribution used before any loan money is drawn.
For the final payment, lenders often want a final valuation and building insurance. Our construction loans guide covers interest during the build and time limits.
How approval timing affects your loan
- Loan approval can come first. Some lenders approve the loan and then give you a set time to supply the approved plans. Check that deadline against how long your approval route is likely to take.
- Deadlines to start and finish. Lenders set limits on when building must start and finish. A DA followed by a construction certificate has more steps than a CDC, so allow for them.
- If you’ve bought the land. If you borrowed for the land, those repayments keep running while your approval is assessed. Our land loans page explains how land and build loans fit together.
- The deposit to your builder. NSW Government says the most a builder can ask for up front is 10%, and where home building compensation cover is required, it’s illegal for the builder to ask for that money until the cover is in place and you have the certificate.
If the plans change
- Conditions of consent can change your design, and so the contract price.
- A modification. NSW Planning says you can apply to modify a consent under section 4.55, if the changed development stays substantially the same.
- Tell your lender. The valuation and loan amount were based on the plans and contract it was given. A new price or new plans can mean a new valuation, and a gap you may need to cover yourself.
Which route fits?
That depends on your lot, your design and your council’s plan, not on the loan. A planning certificate from your council shows the zoning and planning controls for your lot, and your council or a certifier can tell you whether complying development is open to you. Whether to build, and which route to take, is your decision with them.
General information
This guide is general information only. It was prepared without taking into account your objectives, financial situation or needs, and it isn’t planning, legal or financial advice. Check the rules for your lot with your council or a registered certifier before you design or sign anything.
How a broker helps
Your council or certifier handles the approval, and your builder the contract and the build. We help with the loan side: which lenders on our panel will fund your build, what each needs before the first progress payment, and how its deadlines fit your approval route. Whether a loan suits you depends on your situation, so we start by asking about it. For home loans, you don’t pay us a fee. Lenders pay us a commission if you go ahead with a loan. Lender fees may apply.
Sources: NSW Department of Planning, Complying development (updated 26 June 2026), Exempt and complying development policy (updated 26 June 2026), Exempt development (updated 23 October 2026), Local development (updated 4 May 2023), Lodging your development application (updated 4 May 2023), Determination (updated 20 August 2025), Get your construction certificate (updated 4 May 2023) and Low and mid-rise housing: frequently asked questions (updated 17 December 2025); NSW Planning Portal, What is complying development? (updated 25 June 2026); NSW Government, Approvals needed for your building project and Building contracts (updated 29 April 2026); Service NSW, Home building compensation cover (last published 9 September 2024); Campbelltown City Council, Complying development. All read 27 November 2026. Correct as at 27 November 2026. Rules and lender policies can change.
General information only. It doesn’t consider your objectives, financial situation or needs, and it isn’t tax, legal or financial product advice. Lending criteria, fees and charges apply.