How Much Does It Cost to Build a House?

The ABS publishes an average for what a new house is worth when it’s approved, but your build will have its own number. Here’s what that average covers, what it leaves out, and what to get quoted ahead of signing a building contract.

The short answer

For the 2025–26 financial year, the ABS reported an average approval value of $517,430 for a new private house in Australia, up 5.0% on $492,931 the year earlier. That’s the value of the building work estimated when the house is approved. The ABS says it should leave out the land, demolition and landscaping, so it isn’t what a new home costs all up. Your own build depends on the design, the block, the builder and what’s included in the price. On top of the contract, allow for approvals and fees, any work outside the contract, variations and, if you’re moving out, somewhere to live. This is general information, not advice.

Not ready to talk? Get the First Home Buyers guide by email →

Pricing up a build?

We compare how lenders on our panel handle construction loans: what each needs from your contract, how payments are released and the fees, ahead of you signing.

Start Online

or Book a Call →

For home loans, you don’t pay us a fee. Lenders pay us a commission if you go ahead with a loan. Lender fees may apply.

Figures and rules below are correct as at 27 November 2026. The ABS figure is a national average. The fee and contract rules are NSW’s; other states have their own.

What the ABS average tells you, and what it doesn’t

The ABS counts the value of new houses approved by councils and other approval bodies. For a private house, it reported:

PeriodAverage approval value
2024–25 financial year$492,931
2025–26 financial year$517,430 (up 5.0%)
June 2026 (one month, original terms)$529,790

What the figure covers, in the ABS’s own terms:

  • Building work only. The ABS says these values should exclude the value of land, demolition and landscaping, but include site preparation costs.
  • An estimate at approval. It’s the value of the work when completed, as reported when the house is approved, often ahead of final costs and contracts being settled.
  • A national average. It covers new private houses across Australia, so it isn’t a figure for your suburb, your design or your builder.

So treat it as a reference point, not a budget. Your budget starts with your builder’s quote and contract.

What’s in a build price

Two quotes with the same headline price can cover very different things. Ahead of comparing them, find out what each one includes.

  • Base price and inclusions. The NSW Planning Portal says a project home package has certain inclusions in the base price, and if you want to add or change designs, fixtures and furnishings, you may face extra costs. It says to look carefully at what’s included and excluded when you compare quotes.
  • Prime cost items. NSW Government says items that can’t be priced until work starts are listed as prime cost items, and the builder should allow a price that covers their expected cost. The ACT Government gives examples such as stoves, heating, tiles, carpets, taps, bathroom fittings and light fittings, and says you pay the difference if you choose a dearer item.
  • Provisional sums. An allowance for work that can’t be priced exactly until it starts. The ACT Government says it’s typically site work, covering things such as rock.
  • Fixed price or not. The NSW Planning Portal says that if your contract isn’t a fixed price, the cost of labour and materials can increase throughout the project.

Site costs

Site costs are what it takes to get the block ready to build on, and they depend on the land. The NSW Planning Portal says:

  • a land surveyor prepares a detailed survey of your land and the blocks next to it, and council requires it for a development application or complying development certificate. Check whether your builder’s package includes it
  • depending on your land, your builder may ask for an analysis of what’s below the surface, because the soil type decides the footings or slab your design needs
  • you may be asked for a small deposit at the preliminary quote stage for site assessments and soil testing.

If site work sits in your contract as a provisional sum, ask how the allowance was worked out and what happens if the work costs more.

Approvals, certificates and levies

On top of the build, the NSW Planning Portal lists costs that come with getting approval:

  • Development application fees, charged by your council, which vary between council areas. A complying development certificate is paid to the certifier, who discusses payment with you.
  • A BASIX certificate. Every new home in NSW must meet the Building Sustainability Index, and you pay for the certificate.
  • A construction certificate, if fees apply. Check with your council or certifier.
  • Referral fees if your application has to go to another NSW Government agency, and an infrastructure contribution or levy for some new builds. Your council can tell you if either applies.
  • Builders’ preliminary fees. Most builders charge for the inspection, planning, design and preparation of your home, and the amount depends on the builder, the land and the design.

The long service levy. Service NSW says the levy applies to NSW building work of $250,000 or more (including GST), at 0.25% of the total cost of the work, and must be paid ahead of building work starting. Ask your builder whether it’s in the contract price.

Connecting water, sewer, power and gas can also carry costs. Ask your builder which connections the contract covers and which you arrange yourself.

Building soon? Let’s line up the finance ahead of you signing the building contract.

Book My Home Buying Chat

Variations: when the price changes

A variation is any change to the contract once it’s signed, and NSW Government says nearly all of them change the price. Its rules:

  • variations must be in writing, signed by both of you and attached to the contract
  • the variation must explain the cost and show how the price change was worked out.

Settling your selections at the start, rather than during the build, means fewer variations. The NSW Planning Portal also warns that build projects often carry extra costs, such as variations, delays and materials. Keep money aside for variations and anything outside the contract, because extra costs often fall to you.

The deposit and progress payments

  • Deposit. NSW Government says the most a builder can ask for is 10%.
  • Insurance first. For contracts over $20,000, the builder must give you a home building compensation certificate. Until it does, it can’t ask for a deposit or any other payment.
  • Cooling-off. A large job contract (over $20,000) must state a cooling-off period of five clear business days after you’re given a copy.
  • Progress payments. Contracts over $20,000 must have a progress payment schedule. Payments can be fixed amounts after set stages, paid as the work is done, or a mix, and NSW Government says they must match the work carried out.

If you’re borrowing, a construction loan usually pays the builder at each stage, and you pay interest on what’s been drawn so far. Our construction loans guide explains the stages, and the construction loan calculator shows the interest stage by stage at the rate you enter.

What to get quoted ahead of signing

Ask each builder to put these in writing, so you can compare like with like:

  1. What the base price includes, and the full list of inclusions.
  2. Every prime cost item and provisional sum, with the allowance for each and how it was worked out.
  3. Site costs: survey, soil testing, earthworks, and what happens if rock or poor soil turns up.
  4. Which approvals, certificates and levies are in the price, and which you pay yourself.
  5. Which service connections are included.
  6. Whether the price is fixed, and what could change it.
  7. The deposit, the progress payment schedule and the building timeline.
  8. What’s outside the contract, such as landscaping, driveways, fencing and window coverings.

Then add the costs that sit outside any building quote: the land and its stamp duty if you’re buying it, loan costs, and rent if you’ll live somewhere else during the build. The NSW Planning Portal says to count rent among the key building costs.

What lenders look at for a construction loan

Moneysmart describes a construction loan as a type of home loan for people building their own home, and the NSW Planning Portal says most people finance a project home with one. Lenders generally look at the building contract, the approved plans, insurance, a valuation of the finished home and whether you can repay the full loan once the build is done, and our construction loans guide sets out what they ask for.

How we help

We work on the loan, not the build. We compare how lenders on our panel handle construction loans: what each needs from your contract, how it values the plans, how payments are released, the time limits and the fees. Whether a loan suits you depends on your situation, so we start by asking about it. You decide.

For home loans, you don’t pay us a fee. Lenders pay us a commission if you go ahead with a loan. Lender fees may apply.

Sources: Australian Bureau of Statistics, Dwelling approvals rise in June 2026 (released 30 July 2026) and Building Approvals, Australia methodology (July 2026); NSW Planning Portal, MyHome Planner: Plan and MyHome Planner: Approve; NSW Government, Contracts for residential building work (last updated 29 April 2026) and Consumer Building Guide (updated 10 February 2026); Service NSW, Pay the long service levy (building and construction) (published 26 June 2026); ACT Government, Costs to consider; Moneysmart, Construction loan (last updated 1 October 2019). All read 27 November 2026. Correct as at 27 November 2026. Figures, fees and rules can change.

Daniel Innes
Daniel Innes

Mortgage Broker at My Finance Consultants. Daniel compares home loan options from a panel of 40+ lenders for refinancers, investors and home buyers, by phone, at a time you pick online. About Daniel

General information only. It doesn’t consider your objectives, financial situation or needs, and it isn’t tax, legal or financial product advice. Lending criteria, fees and charges apply.

Questions

Common questions, straight answers.

How much does it cost to build a house in Australia?

The ABS reported an average approval value of $517,430 for a new private house in the 2025–26 financial year, up 5.0% on $492,931 in 2024–25. That’s the value of the building work estimated when the house is approved. The ABS says it should leave out the land, demolition and landscaping, so it isn’t the total cost of a new home. Your own cost depends on the design, the block, the builder and what’s included.

What are site costs when building a house?

The costs of getting the block ready to build on. The NSW Planning Portal says councils require a detailed land survey, and your builder may want a soil analysis, because the soil type decides the footings or slab your design needs. Site work can be listed in the contract as a provisional sum, an allowance for work that can’t be priced exactly until it starts, such as dealing with rock. Ask what your quote includes.

What is the difference between the base price and inclusions?

The NSW Planning Portal says a project home package has certain inclusions in the base price, and adding or changing designs, fixtures and furnishings can cost more. Compare what each quote includes and leaves out, not just the headline price.

What are prime cost items and provisional sums?

Prime cost items are allowances in the contract for items that can’t be priced until work starts, such as taps, tiles or appliances. The ACT Government says you pay the difference if you choose a dearer item. A provisional sum is an allowance for work, such as site works, that can’t be priced exactly until it’s done. Both can move the final price, so ask how each was worked out.

How much deposit can a builder ask for in NSW?

NSW Government says the maximum deposit is 10%. For contracts over $20,000, the builder must first give you a home building compensation certificate. Until it does, it can’t ask for a deposit or any other payment.

How do progress payments work?

In NSW, contracts over $20,000 must include a progress payment schedule, and NSW Government says progress payments must match the work carried out. If you’re borrowing, a construction loan usually pays the builder at each stage, and you pay interest on what’s been drawn. Our construction loan calculator shows the interest stage by stage at the rate you enter.

What does it cost to use a mortgage broker?

For home loans, you don’t pay us a fee. Lenders pay us a commission if you go ahead with a loan. Lender fees may apply.

Talk it through with a broker.

No obligation. No pressure. Just honest answers.

For home loans, you don’t pay us a fee. Lenders pay us a commission if you go ahead with a loan. Lender fees may apply.

Rated 5.0 from 21 Google reviews

Read the reviews →
Start Online
“Daniel was awesome. Easy to work with, very helpful and professional. Highly recommend!!”
Benjamin P. · Google
“Great service and really listens and puts the customer first”
James P. · Google
“Professional and quick. Thank you look forward to working with you again”
Kaella F. · Google
Start Online Call